A new two-storey detached house with a double garage, on a rural plot at Bakers Lane in Black Notley, Essex. The plot has no connection to the public sewer, so the drainage is dealt with on site. Lough Build is the main contractor and the house is under construction.

Details

  • Client: Mr & Mrs Lewis.

  • Property: New detached house and double garage

  • Started: March 2026

  • Location: Black Notley, Essex

  • Status: Under construction

  • Budget: Undisclosed

See it being built

What better way to choose your builder than to watch one at work? Bakers Lane is a live Lough Build site, and you’re welcome to come and walk round it. See how the site is set out and run, ask whatever you like, and talk through your own project while you’re there. Site visits are by appointment.

Managed from start to finish

ddddddddddddddd.jpg

We set the house out on the cleared plot and poured the trench foundations in March 2026, with compressible board against the trench sides and test cubes taken from the pour. Above ground, the walls are blockwork cavity construction on an engineering-brick substructure, with a steel goalpost frame, a CaberDek first-floor deck and a trussed roof with a framed gable dormer.

hhhhhhhhhhhhhhhhhhhhhhh.jpg
IMG_1957.HEIC

Drainage and garage

There is no public sewer near the plot, so we installed two on-site drainage systems, one of them a drainage recycling system set in a deep excavation, with new drainage runs and inspection chambers to the house. The double garage sits on its own reinforced slab, poured separately from the house foundations.

The build

Groundworks and drainage

fwe we ewwee.jpg
IMG_2530.JPEG
The cleared plot set out with pegs and line marking, ready for the foundation dig.

Setting out. Plot

IMG_2630.JPEG
Compressible board fixed against the trench sides, with OSB shuttering in place before the pour.

Foundations. Trenches

IMG_2631.JPEG
Concrete poured in the foundation trenches, with the shuttering braced in timber.

Foundations. Pour

IMG_2623.JPEG
A test cube taken from the foundation pour, for strength testing.

Concrete. Testing

IMG_1855.HEIC
The two on-site drainage systems delivered. The plot has no mains sewer, so both are installed on site.

Drainage. Delivery

IMG_1931.HEIC
The deep excavation for the on-site drainage recycling system, with the riser going in.

Drainage. Excavation

IMG_1851.HEIC
New drainage runs laid in the trench, with inspection chambers set in.

Drainage. Chambers

The build

Walls, floors and roof

cdcdcdddddddd.jpg
5t5t5t5t.jpg
Engineering brick and blockwork laid below the damp-proof course.

Substructure. Brickwork

5555yyyy.jpg
The steel goalpost frame standing on the ground-floor substructure.

Steelwork. Frame

IMG_1920.HEIC
Ground-floor blockwork walls going up, with the window openings formed.

Walls. Ground floor

IMG_1961.HEIC
The first-floor deck laid in CaberDek boards across the whole floor.

First floor. Deck

IMG_1990.HEIC
First-floor blockwork going up, seen from the scaffold.

Walls. First floor

IMG_2103.HEIC
Roof trusses going up on the wallplate.

Roof. Trusses

IMG_2139.HEIC
The gable dormer framed and boarded in plywood.

Roof. Dormer

IMG_1994.HEIC
The double garage slab: mesh reinforcement on spacers over the membrane, ready for the pour.

Garage. Slab

IMG_2160.HEIC

Building the roof

The roof is built with trusses on the wallplate and a framed gable dormer boarded in plywood. Foil-faced insulation goes between the rafters, and the membrane and fascias follow on at the eaves.
IMG_2171.HEIC