Hutton Mount
A single-storey rear extension to a detached house on Hutton Mount in Brentwood, completed in 2025. The client wanted a bigger kitchen and dining space opening onto the garden.
We built the extension in blockwork with a flat roof and two rooflights, then took out the back wall of the house so the existing room and the extension became one open-plan kitchen-diner. The wall above was propped and needled while the opening was formed and the new steels went in. We then fitted out the room, including the kitchen.
Groundworks to fit-out

We ran every stage on site: foundations and slab, blockwork walls, the flat roof and rooflights, propping the back wall and putting in the new steels, then insulation, services, plastering, flooring and the kitchen fit-out.


One point of contact
The extension was built to the client's design and signed off by building control on completion. Lough Build managed the work on site from the first trench to the finished kitchen, and the client had one point of contact throughout.
The build
Groundworks and shell


Foundation trenches dug along the back of the house, ready for concrete.
Foundations. Rear

The foundation trench running alongside the house towards the garden.
Foundations. Side

The concrete slab cast inside the new brick footings.
Slab. Ground floor

The blockwork walls going up off the slab, against the back of the house.
Blockwork. Walls

Blocks and insulation boards on site as the walls went up.
Materials. Blockwork

The shell built up to roof level, with the roof joists going on.
Roof joists. Exterior

Inside the shell, with the roof joists in and the openings trimmed for the rooflights.
Roof structure. Interior
The build
Opening up and fit-out


The roof deck with both rooflights fitted, before the covering went on.
Rooflights. Roof

Inside the existing room, with the wall above the French doors propped before it was taken out.
Propping. Interior

The new steel beam and post in the opening, with floor insulation going down.
Steelwork. Opening

The steel post in place and the floor joists going down across the extension.
Floor joists. Extension

The floor boarded and the ceiling joists in, ready for services.
First fix. Extension

The walls plastered and the steel post boxed in, under one of the rooflights.
Plastering. Extension

Opening up the back wall
To join the extension to the house we took out the back wall. The wall above was propped and needled while the opening was formed and the new steels went in, so the house stayed supported throughout. The existing room and the extension now work as one open-plan kitchen-diner.

Details
-
Client: Private
-
Property: Single-storey rear extension to a detached house
-
Duration: 4 months
-
Location: Hutton Mount, Brentwood, Essex
-
Contract: Build and fit-out, to the client's design
-
Budget: Undisclosed
-
Sign-off: Building control
Talk it through in confidence
If you'd rather discuss your project privately, we offer a free 30-minute Teams meeting. You can talk through what you have in mind, what's possible on your site, and how we'd approach it. Where it would help, we can also arrange a free site visit. Everything you share stays confidential, and we're happy to sign an NDA before we start.